THE PROCESS

Weeks 1 - 3

 

Once this proposal has been approved we start furniture detail

designs & procurement to supply you with a quote.

Meet and finalise the design, plans & quotes.

These plans include the following:

Floorplan

Construction plan

Demolition Plan (if needed)

Ceiling layout

Floor layout & finishes

Wall layout & finishes

Shopfront & Signage

Electrical layout

Lighting & Plugs Layout

Cable tray & Downlights Layout

Plumbing & Services

4 x Sections

Details: Glass & aluminum.

Details: Kitchen

Details: Bathrooms

Details: Custom Furniture

Details: Walls (if needed)

design & procurement

IMPLEMENTATION & DELIVERY

HANDOVER & CLOSEOUT

Weeks 4 - 7

Work starts once deposit is paid.

Project timeline shared with client.

Plan the fit; ordering materials, furniture and establish site.

Fit out

Project Management

Cost management & Reporting

Weeks 8

Client handover meeting

Occupation Certificate (if required)

Closeout Documentation


*Allow a further 2-weeks for snagging corrections